2025-5-20
The company is a newly launched characteristic energy power generation project in the wood industry sector, with a backpressure model, with an installed power of 35MW. In addition to production and self-use, the waste steam is supplied to the park for heating. The unit model is B35-8.83/0.98, the flow is 1 single + 16 level, and it is a multi-stage pressure-level high-efficiency model. The installed power of the turbine and generator is 35MW, with an over-transmission margin of 10%. This project was signed on January 18, 2025, with a production cycle of 165 days. It is expected that this project will be supplied on August 10, 2025, and will be powered on and connected to the grid before the end of October to create energy saving and efficiency.
Anhui Yuteshuang Energy Conservation Technology Co., Ltd Copyright Anhui ICP No. 15016561-3disclaimer