2020-1-19
On January 5, 2020, our company was commissioned by Dongying Xishui Group Thermal Power Co., Ltd. to conduct energy-saving diagnosis and appraisal of its back pressure variable working condition transformation project of its extracted condensation 60MW steam turbine unit.
Our company analyzed and appraised the project background, necessity, operation status before unit transformation, technical transformation implementation plan, operation status after unit transformation, and energy-saving benefits after transformation, and gave appraisal opinions: This project is an energy-saving and environmental protection transformation project in varying working conditions, which meets the current national energy-saving and environmental protection and industry policies, and meets its own production process needs. The unit operation is stable and normal, and the energy-saving effect is significant.